The fourth mainland bridge in Lagos is being built, and the Lagos State Government is receiving updates via the Office of Public Private Partnerships.
The Special Adviser to the Governor on PPP, Mr. Ope George, gave a brief overview of the 4th Mainland Bridge project during a media briefing today in Lagos.
He claims that the 4th MB is a proposed Public Private Partnership transportation infrastructure development that entails the building and operation of a toll road and bridge with a design speed of 120 km/h as well as the development of nearby real estate.
Mr. George claims that the bridge, which has three toll plazas, nine interchanges, a 4.5 km lagoon bridge, and an eco-friendly setting, is anticipated to become the second longest in Africa.
Mr. Ope George further disclosed that the 4th MB project has gone through the competitive bidding process, the request for proposal Stage 1 (RFP 1) and the request for proposal Stage 2 (RFP 2). The RFP Stage 2 was then issued to three shortlisted bidders, namely:
1. Mota – Engil (Nig & Africa) CCCC & CRBC consort.
2. CGGC – CGC Joint Venture.
3. CCECC & CRCCIG Consortium.
Conclusively, the Special Adviser disclosed that the Evaluation Committee, which comprises of representatives from the LASG, Ministry of works, OPPP and the project Advisers, commenced the evaluation of the submitted RFP Stage 2 documents on the 17th November, 2022, with the announcement of the preferred bidder to be publicised before the end of the year 2022.✍️✍️✍️ ✍️“feel free to disagree in the comments 👀 ☝️👆 & let JAIYEORIE know what U think!” 📎 COMMENTS 👈👉✍️🤳 DROP YOUR OPINIONS ✍️✍️✍️